• Confined Space Remote Demolition, Diamond Drilling & Sawing Specialists
  • tel 01748 826046

Bridge Road Deck Renovation

This Hydrodemolition Project project required the removal of 150mm depth of damaged concrete to approx 25mm below the last reinforcement bar, in preparation for the reconstruction of a new road surface.

The powerful pump units, delivering pressure outputs ranging up to 36000 psi, accurately removed the defective parts of the concrete structure, cleaning the rebar whilst leaving it and the remaining sound concrete intact and ready for refurbishment.

The Hydrodemolition process is more accurate than other methods, notably hydraulic power tools, because the process is vibration-free. The Ultra High Pressure Water jets can be applied with great accuracy and with little impact on surrounding areas and materials

Get in touch to discuss your project with our hydrodemolition team

After Hydroblasting, the defective concrete is removed, exposing and cleaning intact re-bar